Overview: The East Longmeadow Pool Building Committee convened to discuss advancements in the pool project, including reaching the 60% construction document milestone and reaffirming the budget stability. These developments are crucial as they move closer to the project’s substantial completion date set for July 2026, coinciding with the high school’s opening.
Overview: In a recent meeting of the East Longmeadow Pool Building Committee, the Scansa team presented a detailed update on the pool building project, revealing construction cost estimates that are slightly below the approved budget. The committee also discussed the project’s design elements, construction phasing, and the impact on local swim activities.