Granby West St Building Committee Explores Cost-Saving Measures in Building Project

In a detailed session, the Granby West St Building Committee delved into various potential cost-saving measures for the building project, with a focus on design modifications, emergency preparedness requirements, and grant opportunities. The committee discussed the total project cost, initially estimated at around $9 million, with potential escalations due to additional expenses such as project management and architectural fees.

0:00Among the most discussed items was the proposal to modify the office layout into a more open plan. This change could result in reduced costs by decreasing the number of doors and automatic door openers needed. The possibility of salvaging existing doors was also considered as a cost-efficient alternative, despite the mixed condition of the doors. Additionally, the committee examined the potential savings of approximately $36,000 by eliminating windows in the gym and opting for an infill wall to improve energy efficiency and reduce heat loss during winter months. The significance of the windows was questioned, with some members suggesting they were not essential.

Further attention was given to the impact of different flooring options for the gym, shifting from traditional gym flooring to vinyl composition tile (VCT), and the exclusion of certain items like a microwave and refrigerator from the cost estimate, assuming existing equipment could be relocated. A discussion on HVAC and lighting systems revealed potential savings from reducing enclosed rooms, although quantifying these savings was challenging.

A critical aspect of the meeting was the discussion on generator requirements for the building. The committee clarified that the current plan includes a standby generator, not an emergency generator. Should the building need to function as an emergency shelter, additional requirements such as upgraded alarms and safety systems would be necessary, increasing costs. The engineers emphasized that an emergency generator would differ from a standby generator in function and expense.

21:17Sound systems and technology grants also took center stage, particularly concerning the senior center programming and larger meeting rooms. The need for a sound system in the cafeteria was highlighted, with discussions on pursuing a $16,000 grant to fund audio-visual equipment. The committee weighed this against site accessibility requirements, which were addressed with strategies to minimize costs while ensuring compliance.

The meeting covered site costs, with a major reduction in curbing from 3,000 to 420 linear feet, focused around parking and sidewalks, and the decision to eliminate landscaping costs. Drainage adjustments contributed to a total site cost reduction of approximately $1.3 million, and the overall construction estimate was updated to reflect these changes, now standing at approximately $10 million, excluding professional fees.

In terms of hazardous abatement, recent discussions led to increased costs due to the reintroduction of elements like generators and transaction counters, alongside necessary electrical work adjustments. This recalibration brought the revised total, after contingencies and soft costs, to approximately $9.9 million. The need for further adjustments, particularly related to hazardous materials, was acknowledged.

Debate emerged over the project’s scope, with concerns about the tight budget and the necessity of specific features. Suggestions to defer painting the mechanical room and gym ceilings to later phases were made, as these areas were deemed in reasonable condition. The committee explored altering office layouts to further reduce costs, though quantifying potential savings remained complex.

43:15Finally, the meeting addressed the timeline for presenting updated figures to the select board. Updates on a kitchen grant application were discussed, with contact made with a representative from Cummington.

Note: This meeting summary was generated by AI, which can occasionally misspell names, misattribute actions, and state inaccuracies. This summary is intended to be a starting point and you should review the meeting record linked above before acting on anything you read. If we got something wrong, let us know. We’re working every day to improve our process in pursuit of universal local government transparency.