Jackson Zoning Board Considers Infrastructure Upgrades Amid Community Concerns
- Meeting Overview:
During the recent Jackson Zoning Board meeting, attention was given to Jersey Central Power and Light Company’s (JCP&L) proposed New Jersey Clean Energy Corridor project. The project aims to upgrade existing transmission infrastructure to support offshore wind power generation, a state-mandated initiative. Board members questioned the necessity of the upgrades, the project’s impact on local energy reliability, and potential environmental concerns, while emphasizing the importance of meeting future energy demands.
1:18:55JCP&L’s proposal involves the installation of 44 new steel monopoles to replace outdated wood poles and lattice towers along a 4.75-mile right-of-way. The project seeks multiple zoning variances due to the differing regulations across the seven districts it spans. The primary driver is to integrate 7,500 megawatts of offshore wind power into the New Jersey grid. However, the project’s timing and necessity were challenged by board members and attendees, some of whom were skeptical about the feasibility of offshore wind development.
One participant noted, “the intent is dead meaning offshore wind is dead; it’s not happening,” reflecting doubts about the viability of these energy projects. Despite these concerns, the project is required to comply with state contracts and regulatory obligations. The proposed upgrades are expected to enhance the reliability and capacity of the transmission network, not only supporting wind power but also accommodating other energy sources.
Further discussions revealed the project’s technical intricacies, such as replacing 60-year-old infrastructure with stronger, more robust steel poles capable of withstanding higher loads and wind speeds. The need for these upgrades was justified by the age of the current system, which has surpassed its life expectancy. Additional benefits include increased reliability for the local grid, particularly as Jackson Township’s population is projected to grow over the next five years.
3:23:31The board also addressed environmental concerns associated with the project. JCP&L requested a waiver from submitting an environmental impact statement (EIS), arguing that their project does not meet the threshold criteria outlined in the local ordinance. An environmental consultant explained that best management practices were employed to minimize impacts, including avoiding tree clearing and using matting to reduce construction damage in sensitive areas.
Board members expressed the need for further evaluation. Concerns were raised about the absence of required permits, prompting a request for documentation before the next meeting to facilitate informed decision-making.
2:12:13Questions surrounding electromagnetic fields (EMF) and their potential health risks were also discussed, although expert testimony on this matter was not provided during the session. The project’s compliance with safety standards and the National Electric Safety Code was emphasized, with assurances that the infrastructure would meet necessary clearances and withstand environmental stresses.
1:37:08Despite these assurances, residents voiced concerns about the project’s immediate impact on energy costs, reliability, and potential safety risks. The anticipated upgrades are perceived as addressing long-term needs rather than the community’s issues. The board acknowledged these concerns, emphasizing the importance of balancing future energy demands with present community needs.
3:23:31The meeting concluded with a decision to carry the application to a future date, allowing time for further review and potential scheduling adjustments. The board expressed a commitment to engaging the environmental commission and ensuring that all necessary documentation is submitted to support a comprehensive evaluation of the project’s implications.
Michael Reina
Zoning Board Officials:
Lynne Bradley, Kenneth Bressi, Shira Parnes, Robert Hudak, Moshe Heiman, Sheldon Hofstein, Chrystabel Rosal, Carlos V. Martins, Jason Such, Jeffrey Purpuro (Zoning Officer), Gina Tumolo (Assistant Zoning Officer), Dawn D’Agostino (Zoning Board Clerk), Ryan Murphy (Attorney), Mark Rohmeyer (Engineer), Ernie Peters (Traffic Engineer)
-
Meeting Type:
Zoning Board
-
Committee:
-
Meeting Date:
02/19/2025
-
Recording Published:
02/19/2025
-
Duration:
221 Minutes
-
Notability Score:
Routine
Receive debriefs about local meetings in your inbox weekly:
-
State:
New Jersey
-
County:
Ocean County
-
Towns:
Jackson
Recent Meetings Nearby:
- 04/04/2025
- 04/04/2025
- 83 Minutes
- 04/03/2025
- 04/04/2025
- 91 Minutes
- 04/03/2025
- 04/03/2025
- 120 Minutes